Floor Covering Installer
  Home
  Subscribe
  Subscribe to e-Newsletter
  Subscription Customer Service
  Online
  Today's Top News
  Buyers Guide
  Green
  Career Center
  Tool Bin
  Blog
  Virtual Brochures
  Webinars
  Resources
  Archived Editorial
  Digital Edition Archive
  Classified Ads
  Industry Links
  Water Info Library
  AEC Store
  Market Research
  Product Info (Free)
  Radiant Flooring Guide
  Plumbing Power Book Directory
  Sustainable Plumbing Supplement
  Current Issue
  Ad Index
  Cover Story
  Features
  Columns
  Industry News
  Calendar of Events
  Advertising
  Media Kit
  List Rental
  Reprints
  About Us
  Contact Us
Search in: EditorialProductsCompanies

When is a Project 'Complete?'
by Sam K. Abdulaziz
May 30, 2007

ARTICLE TOOLS
EmailEmailPrintPrintReprintsReprintsshareShare



This article deals with completion on a construction project. However, it is not intended to be a complete analysis of mechanic's liens. For that, you need to seek the aid and advice of a competent construction attorney.

      Contractors are one of the only professions that are allowed to record a lien against property-and tie up that property-to secure their payment even before a lawsuit is filed. The right to a mechanic's lien is protected by the California Constitution. However, the Legislature has tried to balance the rights of the contractors against the rights of owners, and has set forth a number of limitations on enforcement of lien rights.

      One of those limitations is that a mechanic's lien must be recorded within a short period of time after "completion" of a project. If you are the "original contractor," which means the person under contract with the owner, you have 90 days from "completion" of the project to record a mechanic's lien, unless a Notice of Completion has been recorded, at which point, the original contractor has 60 days. A subcontractor's lien rights are shortened from 90 days to 30 days by the recording of a Notice of Completion. The Notice of Completion itself is required to be recorded within ten days of completion. If it is not recorded within ten days of completion, the statute provides that it is ineffective to shorten the lien period and then everyone has 90 days.

      The Legislature has passed a law that would require any one who records a Notice of Completion or a Notice of Cessation of Labor, to send a notice to anyone who gave that owner a Preliminary Notice. The Notice of Completion must be sent by certified mail, within 10 days of recording the Notice of Completion.

The rule requiring notification of the recording of a notice of completion does not apply to a person who occupies the real property as a personal residence so long as the dwelling contains not more than four residential units. Thus, the rule essentially does not apply to owner-occupied homes.

      As to completion, Civil Code section 3086 defines completion to be "actual completion of the work of improvement." However, the statute also provides for "equivalents" to completion: (a) the occupation or use of the work of improvement by the owner, or his agent, accompanied by the cessation of labor; (b) the acceptance by the owner, or his agent, of the work of improvement; (c) a cessation of labor for a continuous period of 60 days (or thirty days if a Notice of Cessation is recorded); or (d) if the work of improvement is subject to acceptance by a public entity, the date of such acceptance.

      Despite what appears to be a fairly clear definition, there have been a number of cases on this subject. In one rather famous case, a contractor was working on a project and there were four soap dispensers the contract required to be installed. The soap dispensers, however, were on back-order. The owner had contended that completion occurred before the soap dishes were installed. The Court of Appeal held that because there was work required under the contract that needed to be performed, that the project was not complete. Accordingly, in that case, the court held that the omission of the four soap dispensers that were part of the contract meant that the project was not complete, and a mechanic's lien that was recorded later in time from the date that the owner declared it to be complete, would be valid. However, in other cases, the Court of Appeal has declared "trivial" or "punch list" work does not extend the time for completion. This becomes a factual question as to whether the work was merely to correct the work originally performed, or to perform work that was required by the contract that was never installed.



Sam K. Abdulaziz
info@agrlaw.net
Attorney Sam Abdulaziz of Abdulaziz & Grossbart has been practicing construction law for 30 years. He has written a book called "California Construction Law" which is updated annually. He represents numerous construction trade associations and contractors. He appears at Contractors State License Board meetings and has argued a number of cases before the appellate courts, including the California Supreme Court dealing with the "Pay-If-Paid Clause." Abdulaziz & Grossbart provides this information as a service to its friends & clients. The documents are of a general nature and are intended to highlight areas of the subject matter and should not be used as a substitute for specific legal advice. You should seek the aid and advice of a competent attorney and/or accountant instead of relying on the presentation and/or documents. Sam Abdulaziz can be reached at Abdulaziz & Grossbart, P.O. Box 15458, North Hollywood, CA 91615-5458; (818) 760-2000, FAX (818) 760-3908.On the Internet, visit our Web site at www.aglaw.net.

|PrintEmail

Did you enjoy this article? Click here to subscribe to the magazine.












BNP Media